Plumbing Dab-outs

In order to protect the plumbing from the concrete during the pour, after the pipes for Showers, Toilets and Bathtubs are cut to 1/2″ below the finished surface, sealed with duct tape and then protected with cardboard. For the toilet drains, three layers of cardboard is fitting around the PVC and one layer of cardboard is cut to size for the top. For shower and tub drains, a cardboard box is cut to the correct height, filled with filldirt and sealed shut. A small amount of fill dirt is placed on the box flaps to hold its position. This allows the concrete to be poured and smoothed right over the tops of these drains. After the pour, the openings can be accessed by chipping away the small amount of concrete on the tops.

Measuring height for the cut..

Marking the pipe...

Cutting the pipe...

Cut to correct height...

Duct tape top...

Completely sealed...

Box cut to correct height...

Fill with fill dirt...

Level fill dirt

Toilet drain dab-outs are slightly different, so a separate set of photos also follow:

Toilet drain

Cut toilet drain to height...

Duct tape...

Check height...

Cut box to correct height using excellent multitool.

Using the saw as a straight edge...

Wrap cardboard around toilet drain.

Three layers of cardboard...

Cardboard cap for good measure.

2 comments to Plumbing Dab-outs